As a result of an extremely tight vote in late March (128 voted in favor and 115 against), the Colchester Fire District no. 3 is dissolving and transferring all assets and liabilities to Champlain Water District (CWD).
At the selectboard’s July 26 meeting, Joe Duncan, CWD manager and Karen Richard, Colchester CWD representative, offered an update on the transition.
Properties on East Lakeshore Drive, Severance Road, Sunderland Woods/Rathe Road to Hercules Drive, the Village Area, Westbury Park and Winchester Place (Route 15) to Bayside Park as of July 1 are now operated by CWD.
In March, the Prudential Committee, the committee formerly in charge of CFD no. 3, recommended the change saying that the current model was unsustainable and that consolidating town water systems under the direction of a professional water system would ensure clean and affordable water for domestic use and fire protection.
“The Prudential Committee saw a need to get out of the business of running it and was looking for a more stable municipal entity to do so and we are happy to be there,” Duncan said at the meeting.
CWD now owns and operates the district, handling all calls and concerns, Duncan said.
In terms of a long-term vision however, Duncan said the goal is for CWD to consolidate the four districts CWD currently owns and transfer ownership to Colchester.
“We’re a believer that the Town of Colchester should be the owner of a water system,” Duncan said. “Because the idea is that, we provide the water, you control your own destiny. You decide where you want growth to go, where you want to extend your water line. We [CWD] don’t want to be the people to decide where your water lines go.”
Duncan said the infrastructure for the district is in good shape, but in terms of getting the bills out to folks, some complications with the transfer paperwork have delayed it a little bit. He said he expects bills to be sent out in mid-August.
In addition, CWD is holding a bond vote Sept. 13 for two projects at the treatment plant: replacing a filter water tank that disinfects the water and adding more lines that pump water from the lakewater pump station to the treatment plant.
The project comes out to around $8.7 million dollars, 80% of which, $6.96 million, is set to come from federal dollars.
CWD has to bond for the whole project but only pay back $1.74 million.
Duncan said that CWD’s five-year plan includes these projects at the $8.7 million cost. With the federal money, the district would be paying 20% of that.
There will be no increase in the water rates served by CWD as a result of the bond.
Residents can travel to 403 Queen City Park Road South Burlington, VT to vote between 7 a.m. and 7 p.m. or by absentee ballot.