'We’ll keep searching:' Planned solar site for Mercier Drive falls through

Posted

The solar site planned for Mercier Drive, which would bring the town to its goal of using 100% renewable energy for municipal services, has fallen through.

At the Colchester selectboard’s Jan. 10 meeting, Colchester town manager Aaron Frank said the ground is too wet for the solar they had hoped for.

In February of last year, the selectboard approved $32,000 for the permitting of the 2.75 acre site, but at this past Tuesday’s meeting Frank said the town was able to catch the situation before any permitting fees were paid.

Frank said the site was not too wet but just wet enough to not get a permit.

Although there were options to put solar on the site, it would had to have been downsized quite a bit, Frank said.

This marks the second time the plans for a third solar site which would bring the town to 100% renewable energy has fallen through. In September of 2021, the town cancelled plans for a solar farm on Hercules Drive after the Vermont Agency of Natural Resources said the farm would adversely impact the natural area.

Although the news is disappointing, Frank said the town is continuing the search and surveying other options for the solar site, possibly on agricultural land.

“We’ll keep searching and will work hard to meet the selectboard’s goal of generating 100% of the electricity consumed for the provision of municipal services through local, affordable, renewable energy,” Frank said. “So, we’ll keep at it.”