Town presents updated Bay sewer project

Posted

Town officials presented an updated Malletts Bay sewer project draft plan to the selectboard last week, more than six months after Colchester Fire District No. 2 announced it would abandon the endeavor due to financial uncertainty and legal concerns.

“This has been a significant topic of discussion for decades and decades here in this community,” public works director Bryan Osborne told the board. “It really has been an integral part of all of the town’s planning.”

The goals of the project have remained the same throughout, Osborne said: addressing failing septic systems, reducing bacteria levels and increasing the enjoyment of Malletts Bay.

CFD No. 2 began exploring the sewer project in 2007 and originally planned to bring sewers from a municipal treatment plant in Burlington’s North End to Colchester’s Heineberg Drive, Prim Road, Lakeshore Drive and Goodsell Point.

Burlington wouldn’t commit to providing treatment plant space, though, and organizers learned complicated legal maneuvers would be required to work with the portion of Goodsell Point that falls within Colchester Fire District No. 3.

The last estimate for the CFD No. 2 project was $23.7 million and would have run a single-family home more than $2,200 annually — Colchester charges similar properties about $860 to connect to the town sewer system.

The revamped version of the project makes significant adjustments to the CFD No. 2 plan, though Osborne noted his presentation was preliminary and “very much a planning exercise” with final details still up in the air.

Namely, the town’s draft proposal eliminates Prim Road and Heineberg Drive from the service area and focuses efforts on inner Malletts Bay. The move more efficiently targets polution points and reduces the total capital costs by about $8 million, Osborne said.

The town is also recommending a switch to the South Burlington wastewater treatment facility, further reducing the previously projected costs by about $5 million. Burlington and Winooski were other treatment options on the table.

“While the plant physically is furthest away from our service area, it’s important to note that we have existing sewer infrastructure that’s connected to this plant that runs up and down the Route 7 corridor, which gives us multiple points of connection to tie Malletts Bay into,” Osborne explained.

Osborne also recommended Blakely Road serve as the connecting route based on an analysis of permitting, right-of-way and risk.

One key pending detail is the Colchester School District’s participation in the new sewer system. Colchester High School, Malletts Bay School and Colchester Middle School are included within the project boundaries, according to Osborne’s presentation.

Board members unanimously agreed to present the findings to the district and assign a two-month deadline, allowing time for their engineer to review plans before deciding whether to commit to connecting to the sewer system at the time of construction.

“Until we know whether [the school] is in or out, we really don’t know what exactly the project is,” Osborne said. “We really don’t know yet what project we’re trying to refine and proceed with.”

Considering the revised service area, South Burlington option, Blakely Road alignment and deferring some system upgrades, the total cost estimate drops to $13.5 million without and $14.58 million with the school’s participation.

The actual loan amount after accounting for loan subsidy, local option tax money and the state’s Priority Point System funding model is $8.3 million without and $9 million with the school’s participation.

That translates to a $1,200 total annual user fee for a single-family home without and $1,130 with the school’s participation — more than $1,000 less than the CFD No. 2 estimation.

“While we have defined affordability for a single family home at $1,200 per year or less, we are very optimistic that we will be able to produce annual user costs that are significantly lower than this once we advance the project further and begin using more refined data,” Osborne said in a follow up email.

The selectboard will refine final project details after the school makes a decision, including finances and next steps, according to a town-created presentation.

“This is the tip of the iceberg, folks,” Osborne told the board.