The Town has an improved traffic control plan for the initial installation of the sewer pump station near The Moorings on West Lakeshore Drive. The road will not be closed except when construction absolutely requires lane closures. Four flaggers and one traffic control coordinator will adapt to traffic flow patterns. Phases of the project include: Pile Driving, Excavation and Bracing, Installation of Precast Pump Station, Sheet Pile and Bracing Removal and Demobilization.
The entire project will require intermittent flagging to allow trucks and equipment into and out of the work area. More impactful aspects of the project related to traffic include:
A: Pile Driving - Beginning Monday 2/24 at 8:00 a.m. and 24 times total over the course of 3-5 weekdays:
• Traffic will be stopped in both directions for up to 10 minutes to pick up each sheet pile or corner joiner, and thread to adjacent sheet pile
• Traffic will be reduced to alternating one-way traffic flow for up to 25 minutes to drive each sheet pile or corner joiner to a 10’ depth
• Traffic returns to unrestricted two-way traffic flow for 15-30 minutes while driving each sheet pile or corner joiner from 10’ to 25’ depth
B: Installation of four sections of precast concrete structure – one to two days
• Alternating one-way traffic for up to 20 minutes to unload each of the four sections
C: Sheet Pile and bracing removal of 24 pieces of sheet pile plus bracing.
• For the removal of each sheet pile - so 24 times total over the course of 3-5 weekdays: Stop traffic for both directions for up to ten minutes to un-thread from adjacent sheet pile, pull from ground depth, and lay down on ground
• Four periods of alternating one-way traffic for up to 30 minutes to load sheet pile plus corner joiners and bracing onto four tractor trailers for removal off site.
General Information: We will provide an update upon completion of each step above as it is not possible to assign specific dates for each step. The working day for construction is generally from 7:00 a.m. to 5:00 p.m., Monday–Friday. We hope to be completed with step C, sheet pile and bracing removal, by 4/13/25. No lane closures will occur on March 3rd or March 4th due to Town Meeting Day.
Please a) seek alternative routes where possible; b) anticipate the delays these coming weeks; and c) please adjust your schedule as best you can for the anticipated delays.
More info at: https://colchestervt.gov/3291/Malletts-Bay-Sewer
Again, our sincere apologies. Aaron Frank, Town Manager