Town of Colchester completes sewer project pile driving that impacted traffic, works to implement new traffic control plan

Posted

Dear Residents, Visitors and Travelers-

The Town has an improved traffic control plan for the initial installation of the sewer pump station near The Moorings on West Lakeshore Drive. The road will not be closed except when construction absolutely requires lane closures. Four flaggers and one traffic control coordinator will adapt to traffic flow patterns.

Phases of the project include: Pile Driving, Excavation and Bracing, Installation of Precast Pump Station, Sheet Pile and Bracing Removal and Demobilization.

The entire project will require intermittent flagging to allow trucks and equipment into and out of the work area. More impactful aspects of the project related to traffic include:

A: Pile Driving -Pile driving to a depth of 10’ which was the portion that caused impacts to traffic, was completed on 2/25/25. The remaining pile driving from the 10’ depth to 25’ does not impact traffic and will continue until about Wednesday 2/26 at 11:00 a.m.

Excavation and Bracing which requires intermittent flagging to allow trucks and equipment into and out of the work area begins about 11:00 a.m. Wednesday 2/26. This will continue for approximately 4-6 work days. The construction will be shut down on March 3rd and March 4th due to Town Meeting Day. The excavation and bracing phase could last until approximately March 10th.

B: Installation of four sections of the precast concrete structure – one to two days

• Alternating one-way traffic for up to 20 minutes to unload each of the four sections

C: Sheet Pile and bracing removal of 24 pieces of sheet pile plus bracing.

· For the removal of each sheet pile - so 24 times total over the course of 3-5 weekdays: Stop traffic for both directions for up to ten minutes to un-thread from adjacent sheet pile, pull from ground depth, and lay down on ground

· Four periods of alternating one-way traffic for up to 30 minutes to load sheet pile plus corner joiners and bracing onto four tractor trailers for removal off site.

General Information

We will provide an update upon completion of each step above as it is not possible to assign specific dates for each step. The working day for construction is generally from 7:00 a.m. to 5:00 p.m., Monday–Friday. We hope to be completed with step C, sheet pile and bracing removal, by 4/19/25.

Please a) seek alternative routes where possible; b) anticipate the delays these coming weeks; and c) please adjust your schedule the best you can for the anticipated delays.

More info at: https://colchestervt.gov/3291/Malletts-Bay-Sewer

Who to Contact:

Danylo Whalen, Colchester Public Works Engineer at 802-264-5515

Norman J. Baldwin, Colchester Director of Public Works at 802-264-5620