Spring roadwork underway

Posted

Construction has begun along Routes 7/2, 2A and 127 in Colchester, kicking off a multi-phase project slated to last until November.

Erin Lewis, a project manager at the Vermont Agency of Transportation, presented plans to the selectboard and around two-dozen members of the public during a meeting earlier this month.

The project, which aims to “improve mobility” and safety through the often-congested stretch, will add two new traffic signals at the Bay Road and Creek Farm Road intersections that can respond to traffic conditions and allow emergency vehicle preemption.

“The vehicles that are queuing up there now [will] be cleared much more quickly and much more efficiently,” Lewis said. “They’re not going to be sitting there waiting for the perfect gap; it will be very obvious when they can go.”

The signals will go hand-in-hand with new crosswalks, pedestrian buttons and street lighting, Lewis said. A new bike and pedestrian path will also be constructed along a stretch of Route 2A.

VTrans officials said flaggers will direct traffic through one-way roads as needed, but noted the section of Route 7 will be closed for nearly two months, between June 19 and August 4.

Drivers will be funneled through a detour along Route 2A and 127. A temporary traffic signal will control traffic at that intersection, officials said, and “extensive” signage will be displayed.

Lewis also assured residents the construction would not interrupt the 4th of July parade or annual triathlon, both held during the scheduled road closure.

After the road is reopened, workers will

implement an underground pipe and catch basin system to manage stormwater runoff, which will reduce the amount of maintenance needed along ditches, Lewis said.

VTrans will also widen sections of the road, add turning lanes and lower the grade of the hill by about five feet at the Bay Road intersection to improve sight distance.

Selectman Jeffrey Bartley asked whether the speed limit, which switches between 35 and 50 mph, could be adjusted to encourage slower travel through the busy crossing.

The plan doesn’t address this, but VTrans officials told the board it could separately request the change. In the meantime, Lewis predicted the new traffic signal might prompt drivers to slow down as they approach, anticipating a red light.

A handful of business owners were concerned about scheduled water shut-offs and relocated driveways. Citizens addressed more general worries, including increased traffic on their private roads.

“The unintended consequence of this project is going to be traffic that’s going to try and come up Coon Hill Road and then down Middle Road,” Dick Pecor said, wondering whether the town could take any steps to alleviate his predicted influx. “If people have to wait a minute, they’re going to look for another way to bypass this project.”

Lewis acknowledged that potential, but said the agency doesn’t have much power beyond the detour. Colchester Police Chief Jennifer Morrison said the town could discourage large trucks from rumbling down side streets but couldn’t block drivers off altogether.

“As for industrious folks who know the area, there’s absolutely nothing we can do to prevent them from trying to use secondary roads,” she said.

Lewis encouraged residents to contact their public outreach coordinator with any questions at 272-1248. Updates on weekly construction plans can also be found at http://bit.ly/2oGZffB.