COLCHESTER — After two fatal crashes and two years of community advocacy, a safety scoping study is in the works for the intersection of U.S. Route 2 and Clay Point Road in Colchester.
Bryan Osborne, Colchester’s outgoing director of public works, shared a number of updates on the advancement of safety initiatives at the intersection at the selectboard’s meeting this past Tuesday.
The intersection has seen two fatal crashes in just over one year, and after both incidents town residents came together in hope of change. After the first push, the speed limit was reduced on Route 2 in that area from 55 miles per hour to 50. The most recent incident, which took the life of Colchster’s Nicholas Ringuette last July, was followed by a push for more changes.
The town has since put forth a series of recommended actions to improve the corridor’s safety, has taken it upon itself to pursue short- and medium-term solutions within its purview, and has been negotiating with the Vermont Agency of Transportation about what more can be done.
“In October 2023 the town submitted what was actually a second request to VTrans to consider a number of things,” Osborne said. “In March of this year we did get a response from them.”
The long-term improvement the town and residential stakeholders have advocated for is to conduct a scoping study of the area to assess alternative future configurations of the intersection, including a possible signalized intersection or roundabout.
The full list of recommended action items can be found here.
“I think the biggest news that I can report to you is that the scoping process associated with the [recommended] longer-term improvements has now officially been included in the Chittenden County Regional Planning Commission’s Unified Planning Work Program, which is the first step,” Osborne said at last week’s selectboard meeting. “It is cleared for public hearing.”
Osborne said CCRPC staff — optimistically — hopes they will have the study underway early this month. The regional project will be managed by the CCRPC at no cost to the town.
The CCRPC intends to assign one of their retained transportation consultants, Stantec Consulting Services of South Burlington, to this project. The project budget is $80,000.
The scoping study, including the selection of a preferred alternative, is expected to take approximately 6-12 months. Following the completion of the study, next steps will include design, permitting, right-of-way acquisition and other project development tasks.
The CCRPC and VTrans will need to identify funding sources for these tasks, including eventual construction considering other regional and state priorities. Realistically, a 5-10-year time frame should be expected for this overall effort.
For those interested in seeing safety improvements to the intersection, this is the good news.
However, VTrans declined to support any of the number of short- or long-term recommendations put forth by the town, including a further reduction to the speed limit — an initiative strongly supported by a number of Colchester residents — for a variety of reasons.
VTrans also noted changes to the speed limit fall under the jurisdiction of the Vermont Traffic Committee and declined to recommend any further changes to the speed limit to the VTC.
All other short- and medium-term options recommended within the state’s right-of-way on U.S. Route 2 would have to have been implemented by VTrans, were they to happen at all. The proposed options as well as VTrans’ position for each is as follows.
Radar speed feedback signs: Not allowed at this location consistent with the Agency’s policy and guidance for use;
Dynamic warning signs: Would not be effective and present problems with reliability and maintenance;
Extend edge-line and centerline rumble strips: This request could be reviewed in further detail and accommodated through the next paving project through the corridor;
Optical speed bars: Not an appropriate location for this traffic control feature based on the Manual on Uniform Traffic Control Devices (MUTCD);
Guard rail around jug-handle islands: Not a standard application of guard rails and may create other safety issues.
Concurrently, the Town of Colchester has continued advancing short-term improvement options related to town highways that fall under its jurisdiction. These include the following:
Install advanced warning signs for the stop signs on the Clay Point Road approaches: Complete;
Install larger stops signs on all side street approaches along US Route 2, along with solar powered red flashing beacons: All materials are in hand and necessary permits have been secured and they will be installed as soon as time allows considering resources and other priorities.
Install splitter islands on both Clay Point Road approaches: Design work is complete and awaiting review and permitting from VTrans, and construction funding is included in the Town’s FY25 Capital Budget Program.
Still, Osborne believes odds are good that the town will see meaningful action from the state to reconfigure the intersection in the long-term, following the scoping study.
“Based on my experience in working with the [VTrans] for many, many years is that they don't get behind scoping studies that they don’t plan on actioning,” Osborne said. “So that is a really positive signal to me that the agency, at least the current agency, is supportive of seeing something done at that intersection.”
Selectboard member Maureen Dakin asked Osborne at the meeting last week where this scoping study work falls on VTrans’ list of priorities, and Osborne reiterated that he expects the scoping study will be done sooner rather than later and will commence this summer.
More information and history of what’s happened thus far can be found in the June 24 memo from Osborne to the Town Manager’s office linked on the selectboard’s recent meeting agenda.