Construction on Routes 7/2 and 2A in Colchester will start up again on May 21, according to officials from the Vermont Agency of Transportation. The project timeline was pushed back last fall.

VTrans project manager Erin Parizo said crews will mainly focus on the Creek Farm Plaza intersection and installing a shared use path this summer. VTrans hopes to have all work completed by August 24.

Substantive work was originally scheduled to wrap up last year. Crews have widened sections of the road, lowered the grade of the hill before the Bay Road intersection by about five feet and installed a four-way signalized light since Parizo came before the Colchester Selectboard in April 2017.

Parizo said VTrans has learned from last summer’s construction and adjusted some of its plans for this year accordingly after meeting with town officials.

“We were trying to find a compromise in alleviating impacts,” Parizo said.

In-road work won’t start until after 8:30 a.m. to reduce the disruption to school buses and morning commuters, Parizo said. VTrans also pushed back its original start date of April 15 after Claussen’s owner Chris Conant contacted the involved parties and asked them to reconsider.

“We do 85 percent of our year’s sales in 12 weeks, and the 12 weeks [VTrans] wanted to do construction were right in the middle,” Conant told the Sun in November. “I employ 50 employees and during the course of the season; that’s the height of the year. If we ruined two months, that would crucify us.”

A press release from VTrans said construction will cease during Memorial Day weekend and July 3 and 4, as well as for the Colchester Triathlon in late July.

The same was promised last year, but town officials decided to move the Independence Day parade to Blakely Road anyway since construction equipment took up the space in Creek Farm Plaza usually used for staging.

Parizo was unsure if contractors had decided to move their equipment this summer.

“Hopefully by getting people through in the morning, it will be a good compromise,” she said. “We’re pretty excited to finish it.”