New pavement coming to VT Route 15 between Colchester and Essex

Posted

COLCHESTER/ESSEX — New pavement is coming to about three miles of VT Route 15 between Colchester and Essex this summer. 

The project kicks off this Sunday, May 10, with milling at the Colchester/Winooski town line. Crews will mill easterly toward the intersection Susie Wilson Road. Milling will then swap to the westbound lanes, before this phase of the project wraps up by Thursday, May 15. 

Approximately two inches of asphalt will later be added on top, according to the Vermont Agency of Transportation. 

Crews will also complete some guardrail work to repair and replace damaged sections and bring others into compliance with current standards. 

VT Route 15 motorists should expect periodic delays with slower travel during working hours. VTrans anticipates two-way traffic to be maintained. 