March 10, 2025 Colchester, Vermont Town of Colchester Traffic Update for Malletts Bay Sewer

Posted

Work is progressing at the sewer pump station near The Moorings on West Lakeshore Drive. The road will not be  closed except when construction absolutely requires lane closures. Two to four flaggers and one traffic control  coordinator will adapt to traffic flow patterns.  

Phases of the project include: Pile Driving, Excavation and Bracing, Installation of Precast Pump Station, Sheet  Pile and Bracing Removal and Demobilization.  

The entire project will require intermittent flagging to allow trucks and equipment into and out of the work area. More impactful aspects of the project related to traffic include: A: pile driving, B: installation of structure, and C:  C: sheet pile and bracing removal 

A: Pile Driving, Excavation, and Bracing – COMPLETE 

B: Installation of Precast Structure and Backfill – Estimated 3/11 to 3/14 

Four sections of precast concrete structure, which will be installed over the course of one to two days. Expect  alternating one-way traffic for up to 20 minutes to unload each of the four sections. 

The excavation will then be backfilled around the precast concrete structure. Backfilling will require intermittent  flagging to allow trucks and equipment into and out of the work area. 

C: Sheet Pile and Bracing Removal – Estimated 3/17 to 3/21 

24 pieces of sheet piling and bracing must be removed from the excavation. For the removal of each sheet pile - 24 times total over the course of 3-5 workdays: Stop traffic for both directions for up to ten minutes to un-thread  from adjacent sheet pile, pull from ground depth, and lay down on ground. 

Four periods of alternating one-way traffic for up to 30 minutes to load sheet piles plus corner joiners and  bracing onto four tractor trailers for removal off site. 

General Information: We will provide an update upon completion of each step above as it is not possible to  assign specific dates for each step. The working day for construction is generally from 7:00 a.m. to 5:00 p.m.,  Monday–Friday. We hope to be completed with step C, sheet pile and bracing removal, by 3/21/25. 

Please a) seek alternative routes where possible; b) anticipate the delays these coming weeks; and c) adjust your  schedule the best you can for the anticipated delays. 

More info at: https://colchestervt.gov/3291/Malletts-Bay-Sewer 

Contact Information:  

Danylo Whalen, Public Works Engineer, dwhalen@colchestervt.gov 802-264-5515 

Norm Baldwin, Director of Public Works, nbaldwin@colchestervt.gov 802-264-5620

 

Comments

No comments on this item Please log in to comment by clicking here