COLCHESTER — The Malletts Bay Sewer Project is now expected to be completed in 2029 due to rising construction costs and an effort to control traffic.
The Colchester Selectboard heard a presentation from public works engineer Danlyo Whalen on Tuesday about the change in schedule. The project, approved during Town Meeting Day in 2022, was initially expected to be finished this fall but will now take three more years.
The cost of the project has also risen from $16.7 million based on a 2021 estimate and two and a half year timeline to $27.8 million based on a March estimate and five and a half year timeline.
The Malletts Bay Sewer Project is designed to help the environment and reduce lake pollution by adding 289 properties in the Malletts Bay area to the town’s sewer system instead of using private septic systems.
Factors behind this extension include limiting the number of contracts at one time to limit traffic delays, a shortage in workers and more oversight of the traffic control contractor to keep traffic flowing.
Due to the increase in cost of the project, Malletts Bay Sewer Project users will be responsible for collectively paying back a $11.5 million bond with a 2% interest rate instead of a $6.09 million bond as was previously planned. Colchester taxpayers not on the project’s sewer line will not have to pay this. The town also needs to obtain $440,701 in non-taxpayer funds to finish the project, likely through grants.
“That is approximately 1.5% of the project,” Whalen said of the non-taxpayer funds remaining. “We are approaching that with a very high degree of confidence, considering how successful we have been thus far and seeking additional grant opportunities.”
The town plans to reach out to residents in the future to educate them on these changes and what they can expect via social media, the town newsletter and holding public information meetings for those in the project area, among other methods of communication.
Selectboard member Maureen Dakin asked if there was a process to predict the cost increases undertaken at the beginning of planning the project.
Whalen said such a process had been completed but world events had changed costs more than anticipated.
“It is quite common to end up including a construction cost index to estimate the escalated cost of construction over the length of a project, especially when it was initially proposed and designed, and then COVID happened,” he said.
Dakin said she was concerned about the three year extension and what she was going to say to constituents who are concerned if the project is ever going to end.
“I want to know as a selectboard member, and as a citizen too, how does it get explained, other than to say mistakes were made in phase one and in order to correct everything, we're extending this project three years, is that the answer?” she said.
Whalen recommended focusing on the reduced traffic impact for residents and commuters.
“We don't want to make the same mistake twice,” Whalen said. “We've already paid that tuition once, which means that we have to use that as an opportunity to improve our performance in the future.”