Colchester’s 2022 Town Meeting Day warning, approved by the selectboard Jan. 11, includes an article asking voters to approve $16.7 million for the construction of a sewer system in the Malletts Bay area.
The Malletts Bay Sewer Project is the same project that was proposed to voters at Colchester’s Town Meeting Day in 2019. It was voted down at that time.
This year, there is one big difference.
With the addition of grant money from the American Rescue Plan Act, the town is able to offer the project at no cost to the Colchester taxpayers, funding the project through grants and fees only to users of the new municipal sewers.
“It has not changed [from two years ago] other than the addition of the $5.1 million in ARPA and the fact that it doesn't use any form of local tax dollars,” said Town Manager Aaron Frank at the selectboard’s Jan. 11 meeting.
The warning also includes:
The proposed Malletts Bay Sewer Project would construct municipal sewers for 289 properties within or near Malletts Bay. Town officials say it would preserve and protect the bay for future generations, remove human waste bacteria from the bay and ensure the community's vision.
Director of Public Works Brian Osborne said during a presentation for the project at the selectboard’s Jan. 11 meeting, that the project would not be funded through town taxes and would only be paid for by the users of the system.
The proposed service area includes everything on both sides of West Lakeshore Drive from the intersection at Prim Road back to the bayside, all of East Lakeshore Drive and all of Goodsell Point.
Osborne laid out the entities that have reviewed the situation at Malletts Bay and recommended the project, including the Integrated Water Resource Management (IWRM) project, which was a team of scientists and engineers who spent four years studying water quality in Malletts Bay through a $2 million EPA grant.
That team concluded that the best way to address human waste bacteria in Malletts Bay and protect public health was to construct municipal sewers.
In 2019, the Colchester Planning Commission spent seven months doing an alternatives analysis where it compared the predicted outcome of certain actions and compared them including doing nothing, looking at land conservation strategies and looking at using community disposal fields, Osborne said.
That study, which took extensive public input, also concluded that the best possible way to address the problem would be the sewer project.
In addition, the project has the support and recommendation from the Vermont Department of Environmental Conservation.
Osborne said the project is part of a larger public visioning process the town went through for almost a decade with the goal of creating a vision for the community and what the community wanted Malletts Bay to look like.
“The areas that they focused on and concluded that were areas of opportunity for improvement were sewers, stormwater, transportation, recreation, and zoning,” Osborne said. “The Malletts Bay Sewer Project is one part of that overall visioning process.”
The current estimate for the project comes out to about $16.7 million of which 64% ($10.6 million) would be paid for by grants. The remaining 36% ($6.1 million) would be paid by user fees.
The loan used to pay for the non-grant funded portion of the project would be a 30-year 2% loan to the state of Vermont, with an annual payment projected to be around $270,000 for 30 years.
The specific grants used to fund the project would be: $5.1 million of American Rescue Plan Act money, $5.01 million from a Pollution Control Grant and the remaining $500,000 through a Clean Water SRF Loan Subsidy (a loan with loan forgiveness that functions like a grant), Osborne said at the meeting.
Osborne said the average annual cost to users of the new sewer system, including the fixed cost of building the sewers combined with the cost of the utility itself, is comparable to the annualized cost of an average on-site septic system over 25 years.