Malletts Bay Sewer Project: Blakely Road update

Posted

Local contractor Kingsbury Companies, LLC continues force main installation along Blakely Road from Poor Farm Road to Severance Corners. Kingsbury’s work will continue at the following locations:

A: Pump Station – Estimated 4/28/25 to 8/15/25

B: Force Main Installation and Restoration – Estimated 5/5/25 to 7/11/25

C: Blakely Road Crossing and Connection to Existing Sewer – 6/16/25 to 6/20/25, 7:00pm to 6:00am

Local utility contractor, Green Mountain Power, will be installing new utility poles and extending multi-phase power from 883 Blakely Road (Colchester Family Practice of UVMMC) to the pump station site near Shadow Cross Farm. GMP will:

Be working in and out of the right of way, using single lane closures and flaggers where needed.

This work will occur from 7:00am to 5:00pm.

Work’s expected duration is from 6/19/2025 to 7/21/2025.

General Information: The working day for construction is generally from 7:00 a.m. to 5:00 p.m., Monday–Friday.

The dates above are approximate, as construction is not entirely predictable.

Please a) seek alternative routes where possible; b) anticipate the delays; and c) adjust your schedule the best you can.

More info at: https://colchestervt.gov/3291/Malletts-Bay-Sewer

Who to Contact:

Danylo Whalen, Colchester Public Works Engineer at 802-264-5515

Norman J. Baldwin, Colchester Director of Public Works at 802-264-5620