Local contractor Kingsbury Companies, LLC continues force main installation along Blakely Road from Poor Farm Road to Severance Corners. Kingsbury’s work will continue at the following locations:
A: Pump Station – Estimated 4/28/25 to 8/15/25
B: Force Main Installation and Restoration – Estimated 5/5/25 to 7/11/25
C: Blakely Road Crossing and Connection to Existing Sewer – 6/16/25 to 6/20/25, 7:00pm to 6:00am
Local utility contractor, Green Mountain Power, will be installing new utility poles and extending multi-phase power from 883 Blakely Road (Colchester Family Practice of UVMMC) to the pump station site near Shadow Cross Farm. GMP will:
Be working in and out of the right of way, using single lane closures and flaggers where needed.
This work will occur from 7:00am to 5:00pm.
Work’s expected duration is from 6/19/2025 to 7/21/2025.
General Information: The working day for construction is generally from 7:00 a.m. to 5:00 p.m., Monday–Friday.
The dates above are approximate, as construction is not entirely predictable.
Please a) seek alternative routes where possible; b) anticipate the delays; and c) adjust your schedule the best you can.
More info at: https://colchestervt.gov/3291/Malletts-Bay-Sewer
Who to Contact:
Danylo Whalen, Colchester Public Works Engineer at 802-264-5515
Norman J. Baldwin, Colchester Director of Public Works at 802-264-5620