Interstate Exit 16 Diverging Diamond to open overnight Wednesday, Sept. 16

Posted

COLCHESTER — The new Diverging Diamond Interchange traffic pattern on U.S. Route 2/7 at the I-89 Exit 16 interchange in Colchester will be implemented overnight on Wednesday, Sept. 16, weather permitting.

Starting Sunday, Sept. 13, through Wednesday, Sept. 16, crews will be paving and installing line striping and pavement markings within the interchange. This work will take place at night and is highly dependent on the weather.

Paving and striping are critical to the opening of the project and may delay the overnight implementation of the new traffic patterns at the interchange, according to the Vermont Agency of Transportation. 

The interchange design will improve mobility, reduce congestion and enhance safety for motorists, bicyclists, and pedestrians along the U.S. 2/7 corridor. 

The new design was created to shift vehicles to the left side of the road as they travel through the interchange. This design allows drivers turning left onto interstate entrance ramps to do so without crossing oncoming traffic. Once through the interchange, traffic returns to the normal right side of the roadway. Traffic signals will control both crossover points. 