COLCHESTER — Work on the Malletts Bay Sewer Project is restarting for the 2025 construction season beginning April 14.
Local contractor J. Hutchins, Inc. will be installing the sewer mainline on East Lakeshore Drive between Blakely Road and South Bay Circle. Traffic will be impacted, and detours will be required.
East Lakeshore Drive between Blakely Road and Williams Road will be closed—to all but local traffic from April 14 until approximately July 15, Monday through Friday from 7 a.m. to 5 p.m. More details follow in the construction steps below.
Non-local and regional commuting traffic should not use Bay Road, Williams Road, or East Lakeshore Drive from April 14, 2025 until approximately July 15, 2025, Monday through Friday from 7 a.m. to 5 p.m. More details follow in the construction steps below.
Steps of the project include: Mobilization, Mainline Installation, In-road Service Lateral Installation, Pavement Restoration, and Demobilization. Private connections to the sewer system will be completed as a part of a separate contract.
A: Mobilization – Estimated 4/14/25 – 4/30/25
The contractor will roll out their traffic control package, stage equipment, and prepare to begin work. This will include closing East Lakeshore Drive to all traffic, other than local residences and businesses within the corridor, Monday through Friday from 7:00 a.m. to 5:00 p.m.
B: Mainline Installation – Estimated 5/1/25 – 5/13/25
The sewer mainline will be installed below the eastbound lane (furthest from the lake) in sections. Construction teams will be coordinating with residents and property owners regularly regarding advancement of work and access to properties. There will be barricades around the construction site which traffic may not pass by Monday through Friday from 7:00 a.m. to 5:00 p.m. The construction will move a few hundred feet per day beginning at the intersection of East Lakeshore Drive and Blakely Road, heading just north of South Bay Circle.
C: In-Road Service Lateral Installation – Estimated 5/14/25 – 5/29/25
Once the sewer mainline is installed, the contractor will install service laterals from the sewer mainline below the road to the edge of the town right of way. Construction teams will be coordinating with residents and property owners regularly regarding advancement of work and access to properties. There will be barricades around the construction site which traffic may not pass by Monday through Friday from 7:00 a.m. to 5:00 p.m. The construction will move a few hundred feet per day beginning at the intersection of East Lakeshore Drive and Blakely Road, heading just north of South Bay Circle.
D: Paving, Site Restoration, and Demobilization – Estimated 5/30/25 – 7/15/25
The contractor will complete repaving of affected areas, restore greenbelts, and demobilize from the site. The closure to all but local traffic will remain in place during this period, Monday through Friday from 7:00 a.m. to 5:00 p.m.
Detour: East Lakeshore Drive between Blakely Road and Williams Road will be open to local traffic only, Monday
through Friday from 7:00 a.m. to 5:00 p.m. Non-local and commuter traffic are strongly encouraged to divert around the construction area. East of the construction area, traffic should use Bay Road to reach Roosevelt Highway. West of the construction area, traffic should use Blakely Road and West Lakeshore Drive. Williams Road will remain open, however commuters are advised against using Williams Road as a detour, as it is likely to be difficult to access Blakely Road via Williams Road during peak traffic times.
General Information: The working day for construction is generally from 7:00 a.m. to 5:00 p.m., Monday–Friday.
The dates above are approximate. Construction is not completely predictable. It is possible this work could be completed a little early or a month late due to unforeseen conditions or weather. We will not be providing updates as each step is completed since the impact to the traffic will remain the same over the course of this work on East Lakeshore Drive.
More detailed information will be provided to the residents and businesses on East Lakeshore Drive from Blakely Road to South Bay Circle, including how we will address access to properties which are within the barricaded work zone. (This information will not be shared to others.)
The Town has coordinated with the Colchester School District and has made special accommodations for school buses that pick up in this area. This will be communicated to affected parties through the school district.
Please a) seek alternative routes where possible; b) anticipate the delays; and c) adjust your schedule the best you can.