COLCHESTER/ESSEX — Construction on the multi-use path along VT Route 15 has paused for the winter season and will resume in 2022.
When complete, the new path will connect Colchester to Essex by running along the south side of Route 15 from Lime Kiln Road to Vermont Air National Guard Road. It will then cross VT Route 15 and continue along the north side to Susie Wilson Road.
The 10-foot-wide path is multi-purpose and includes pedestrian signal upgrades, signage and pavement markings.
The project was estimated to be completed in October and was later delayed to December. Spring 2022 is the Vermont Agency of Transportation's (VTrans) new completion date.
Construction on the path began in April with excavation and the removal of pre-existing sidewalk. In June, VTrans began paving. Light poles, curbs and pedestrian signals were installed throughout the summer. This fall, minimal on-site construction took place as VTrans worked with utility companies.
The work site is currently being cleaned up for the winter season. In the spring, sidewalks that were paved for winter will be replaced with concrete in spring 2022.