Is the third time the charm?
The Colchester Selectboard sure hopes so. The board authorized Town Manager Aaron Frank on Tuesday to enter into a contract with AEGIS Renewable Energy, Inc, in an effort to permit a solar power generating facility on 8.4 town-owned acres.
The site, located off of VT Route 15 and next to the Fort Ethan Allen Cemetery, is the third proposed site for the town’s third solar farm.
The 150 kilowatt solar facility would complete the town’s goal of producing electrical energy equal to that which the town consumes in the provision of municipal services.
Currently, with the energy produced at the town-owned Pumpkin Patch and Roosevelt sites, 66% of the town’s municipal services is covered by renewable energy.
In a March 28 memo to the selectboard, Frank said the goal of 100% renewable energy accomplishes three important elements, including reduced municipal costs and more local green jobs. It also is an example to residents and private sector businesses that renewables can be done in a cost-effective manner.
“The attorneys and auditors who look at our business documents tell me they have never heard of a government saving 40% of electricity costs through a solar project as we have,” Frank stated.
The estimated construction cost for the system at Fort Ethan Allen is currently $595,500, pending completion of design and verification of landscaping costs.
The town previously proposed two other sites for this solar field, Sunny Hollow and Mercier Drive.
The Sunny Hollow project halted after the Vermont Agency of Natural Resources said Colchester’s application would be denied due to the planned removal of trees that would have an “undue adverse impact” on a “rare, irreplaceable, natural area.”
Mercier Drive fell through when ANR said the soil was too wet.
“The Town Manager’s office, and solar contractor AEGIS Renewable Energy, spent significant time and effort trying to locate a third solar farm,” the memo from Frank to the selectboard states. “This is becoming challenging given the significant permitting constraints, a lack of available town-owned land and our financing model which requires town-owned land to provide the maximum financial benefit and avoid use of taxpayer funding,”
After exhausting its options, the town returned to the Fort Ethan Allen location, which it had evaluated as a possibility in 2017.
The site offers good solar exposure with minimal impact to neighbors, according to the memo, and the solar field will be divided from the Fort Ethan Allen cemetery by a tall row of trees. The town states there would still be significant room for cemetery expansion if needed.
The permitting process for the solar field will most likely take months, so construction, if it occurs, is still some time away.
In addition to this proposed project, AEGIS is working with the Town of Colchester on a solar component to the future Colchester Recreation Center.
Comments
No comments on this item Please log in to comment by clicking here