COLCHESTER — The selectboard approved the funding plan for the Malletts Bay Sewer Project at its meeting Tuesday night, as proposed by town attorney Brian Monaghan.
The agreement, dubbed the Wastewater System Revenue General Bond Resolution for the Malletts Bay Sewer Project, was also recommended by Bryan Osborne, director of public works.
“While it's a number of pages, it really says one simple thing,” said Town Manager Aaron Frank at Tuesday’s meeting. “That the Mallets Bay Sewer debt repayment is only to be repaid from the proceeds of wastewater fees, not from property taxes.”
The Malletts Bay Sewer Project was granted voter approval under the caveat that it’s funded with the revenue bonds, which are loans to be repaid exclusively by wastewater system revenues, as opposed to general obligation bonds, or loans paid by town’s general budget — in other words, the project funding won’t burden Colchester’s taxpayers.
This funding model has been the plan from the get-go. As of Tuesday, it’s been made official.
The full legal document from Monaghan’s office can be found under the Malletts Bay Sewer action item link within the selectboard’s most recent meeting agenda.
Also this week, the Department of Public Works wrapped up a meeting series intended to inform area residents and businesses about what to expect regarding construction and traffic impacts for the sewer project, with the final information session held last night.
In case you missed it, the information presented during those sessions was as follows.
The Malletts Bay Sewer Project will provide municipal sewer service to properties with frontage on West Lakeshore Drive between Prim Road and the Bayside intersection, all of East Lakeshore Drive and Goodsell Point.
Phase one of the project will begin this month and is expected to continue to August of 2025, on Blakely Road, West Lakeshore Drive from Prim Road to the Bayside Intersection and East Lakeshore Drive from the Bayside intersection to just beyond South Bay Circle.
The first phase involves construction work along the aforementioned segments of East and West Lakeshore Drives to install the main sewer collection line, as well as along all of Blakely Road to install a no-access transmission line to connect the East and West Lakeshore Drives’ collection lines to the existing town sewer system in Severance Corners.
Phase one will also involve construction associated with the installation of a wastewater pump station outside the roadway on West Lakeshore Drive, as well as for one on Blakely Road.
Phases two and three will involve additional work along East and West Lakeshore Drives and Goodsell Point, to take place between 2025-2027.
The second phase will extend the main collection line to the rest of East Lakeshore Drive, add service connections for properties on East and West Lakeshore Drives to the new sewer system and decommission those sites’ on-site septic systems, tentatively from 2025-2026.
Goodsell Point will be connected to the new system as part of the final phase, expected to take place in the 2026-2027 timeframe.
To address traffic impacts as much as possible, the DPW will implement several standard traffic control measures throughout project areas to ensure public safety with the least amount of public inconvenience.
These include variable message boards and signage placed in advance of work beginning; safe pedestrian routes through project areas provided at all times as well as emergency service access and access to driveways; coordination with Colchester School District’s bus service, personal routes and trash haulers; and flaggers and uniformed traffic control officers used when required to ensure safe passage of vehicles.
The work to take place on Blakely Road, from June of this year until approximately May of next, will involve limited excavation within the roadway but will generally take place along the road’s shoulder, with minimal traffic impacts expected. The hours at this site will be Monday-Friday from 7 a.m. until 5 p.m.
Work on East and West Lakeshore Drives this and next summer will involve more roadway excavation to install the new sewer lines, so significant delays should be expected and planned for in this corridor.
West Lakeshore Drive will allow work Monday-Friday from 7 a.m. until 5 p.m. and overnight 9 p.m. until 7 a.m. Contractors will be required to maintain at least one-way traffic at all times, controlled by flaggers or uniformed traffic control officers for both standard and overnight work hours. At the end of each work period, the roadway will be reopened to traffic.
East Lakeshore Drive will allow work Monday-Friday from 7 a.m. until 5 p.m. Two-lane road closures will be permitted during standard working hours, with a temporary detour established on Williams Road. Access to private driveways will be maintained at all times. The roadway will reopen to at least one-way traffic at the end of each work day, controlled by temporary portable traffic control signals or another approved method.
The DPW estimates the winter shutdown of construction will take place November-April.
Communication efforts will include a public outreach and communication team formed by the town; notices to be made on social media, the town newsletter, town website, newspaper, Front Porch Forum and brochures; collection of email addresses of those interested in being included on a listserv for regular project updates; coordination with U.S. Postal Service and trash haulers, CSD coordination; notification to neighboring municipalities and use of the Traffic Alert System at Chittenden County Regional Planning Commission and Vermont Agency of Transportation.
All accompanying information about the project, including answers to a number of frequently asked questions, can be found here. Additional questions about the project may be sent to Osborne at MBS@colchestervt.gov or by calling 802-264-5620.