COLCHESTER — Construction on the Diverging Diamond Interchange at Exit 16 is moving ahead, with drilling and blasting work beginning next week.
The blasting to remove hard rock and ledge will occur underground, and there will be no visible explosions, according to the Vermont Agency of Transportation. The blasts are not expected to be loud. Traffic will be impacted twice a day for approximately 10 minutes.
The DDI project at the Colchester/Winooski town line is reconfiguring the existing tight interchange between the intersection of U.S. Route 2/7 and Interstate 89 to better serve vehicles, bicyclists and pedestrians. The entirety of construction is expected to be completed by summer 2026.
In a DDI, traffic crosses to the left side of the roadway, allowing for ease of access to the interstate by eliminating difficult left turns and the traffic signals which currently account for approximately three collisions a month, according to VTrans.
Starting Monday, April 3, the blasting will occur for about two months along U.S. Route 2/7 between South Park Drive and Mountain View Drive. Up to two blasting events will take place a day and will be restricted to weekdays, between 9 a.m. and 3 p.m. The exact time of each blast will vary.
The contractors, S.D. Ireland and Maine Drilling and Blasting, expect no visible explosions such as fireballs, flying debris or major dust clouds. Small rumblings and vibrations in the ground may be felt, but the blasts will not cause buildings to shake or rattle.
Blasting activities are required to facilitate the installation of the west side retaining wall off of the roadway behind the I-89 bridge pier and the relocation of underground utilities within U.S. Route 2/7 including the waterline and electrical and telecommunication utility duct bank.
Four minutes before blasting, all traffic will be temporarily restricted from the blasting area. Flaggers, construction vehicles, rolling roadblocks and audible signals will be used to notify the public of an upcoming blasting event, which includes three whistles to indicate a five-minute warning, two whistles to indicate a one-minute warning and one whistle to indicate the all-clear.
The “all-clear” will be followed by the blasting event. Afterwards, the I-89 interstate offramps will be cleared before U.S. Route 2/7 traffic is released. In total, wait times are not anticipated to exceed 10 minutes.
Daily blasting updates will be posted to the project’s website under “project updates” and on the interactive map.