Thursday, April 16 Correction: This article was updated to correctly state public works engineer Danylo Whalen's first name and to note the correct start date for phase 2 of the Malletts Bay Sewer Project. The story was also updated to clarify that the decision to extend the Phase II timeline was made last year and was not due to rising costs.
COLCHESTER — The Malletts Bay Sewer project is currently wrapping up Phase 1 of construction, with three years left until completion.
Back in 2025, the town extended the Phase II completion timeline to the fall of 2029, due to industry challenges and an attempt to control traffic. The Sun reached out to public works engineer Danylo Whalen to get more details about how the timeline will impact residents and future users of the utility.
Users of the Malletts Bay Sewer will now be responsible for paying back a 30-year bond of $11.5 million, the maximum amount authorized by the 2022 vote, with 2% interest from the State of Vermont Clean Water Revolving Fund, which is funded by the U.S. Environmental Protection Agency.
It was estimated when the bond was approved by voters in 2022 that only about $6 million of the bond would be needed, and it's possible the total bill could go down if the town secures more funding, Whalen stated.
The rising price tag of the project is in part due to nationwide increases in construction costs. The U.S. Bureau of Labor Statistics reports a 47% increase in non-residential construction costs between January 2021 and January 2025.
Whalen stated the project is also struggling to find available construction workers. There are approximately 60 workers available for each 100 jobs in Vermont, according to July 2025 BLS data.
The utility rate approved by the selectboard for 2026 is estimated to cost $124 per month for households on the sewer line using an average of 210 gallons per day.
The project gets its funding from a variety of sources including a State of Vermont pollution control grant that scales with the total project value. The project also uses money from government grants including $800,000 from the Vermont Agency of Community Development, $101,000 from the U.S. Environmental Protection Agency, and a loan subsidy from the Vermont Department of Environmental Conservation for $350,000.
The town still needs to find $440,701 in future non-tax funding sources based on a March estimate for the project. The town is confident that it can come up with the funds, Whalen stated.
Colchester utilizes state and federal grants for a variety of town projects. Of the 29 capital projects scheduled for the current fiscal year, 62% of their total cost is expected to come from state and federal grants.
This includes the Creek Farm Road Bridge Replacement which is mostly covered by two $200,000 grants and the Bayside intersection roundabout and Prim Road/West Lakeshore Drive improvements that are both 100% funded by state and federal grants.
The project is divided into two phases, with Phase 1 involving three contracts and Phase 2 involving four contracts. The three contracts in Phase 1 were estimated prior to the public vote in 2022 to take one year. The time to complete Phase 1 has since doubled. Phase 2 is expected to start on April 20, 2026.
“After completion of design and considering the limited available workforce in Vermont after the mid-COVID societal changes and — along with the growing housing shortage in Vermont — these contracts were estimated to take about two years,” Whalen wrote. “The three Phase 1 contracts were completed in about two years as per the post design estimates.”
Phase 1 is expected to be completed by July 15, 2026 with contract 2 and 3 over 95% complete.
Phase 2 is expected to impact 289 individual private properties, which Whalen stated is unusual for a public project and could’ve been done at a lower cost and more quickly if properties were required to connect to the sewer at their own expense.
Whalen said Phase 2 taking three years instead of the one year that was estimated prior to the design process to “the change in worker availability for construction and design, and the lack of data points for the construction of sewer connections to private properties as this is not normally done by governments.”